School Room & Cloak Room Roof Replacement – Day 17 to 19
Work this week has continued on the other side of the school room roof.
Renovating a Victorian Property in Mid Wales
Work this week has continued on the other side of the school room roof.
First day back after the Christmas break and today work started stripping the oppsosite side of the school room roof. The pictures were taken at the end of the working day and the exposed roof was tarpaulined as snow was … Continued
Part of the scaffolding has been removed today to allow the reslating to continue.
Now this section of the roof is boarded and battened the new slates are now going on.
The cloak room side of the school room roof is now boarded and battened and the slating has begun. Once this is section is completed the mid-level scaffolding can be removed.
A day of 3 stages today. Stage 1: Remaining slates and ridge tiles removed. Stage 2: Exposed boards removed Stage 3: New sarking boards and breathable ridge membrane installed.
More slates and lead work added to both sides of the cloak room roof.